The type of work on the Strakonick Street section should be completed by November 26
Strakonick street in Prague
| photo: TK
Due to the construction of a new lane for public transport, queues are formed in Strakonick Street for several months, especially during rush hours.
The first stage of the new road with a dedicated lane for public transport began last year and was completed this year. Subsequently, the several-stage repair of the Barrandovský bridge began.
At the end of the period, the second stage of the construction of Strakonick Street began. Work harder in the section from the overpass of the overpass of the Mezichuchelsk street to the Mal Chuchle bus stop. The new lane will be reserved for buses, taxi vehicles and the city police.
Now the roadway of the middle lane is paved and the route of the asphalt is laid, which will be completed today. Work will continue in the left fast lane. We expect to complete all the work and put the road into full operation on Saturday, November 26, weather permitting, Likov said.
The amount of asphalt in the left lane is full until Wednesday, November 23. Two days later, the police check the traffic sign in the evening. If it’s good enough, I’m going next November 26, all lanes will open.
Strakonick street is one of the busiest roads in the metropolis. Therefore, the leadership of Prague first decided to divide it by one lane, which will be used by the public transport bus, which regularly takes a big stop on Strakonick Street. During the construction, the contractors replaced the surface with the remains of the road.