Optimization of the line section Prague – Smíchov (outside)
Overview of known restrictions for the month of March 2022 + outlook
Overview of new works for the month of March 2022
- 7/9, the exclusion of track and station tracks was overturned and tracks 1 and 3 from km 3.4 – 9.3 and the underpass at km 10.221 were reconstructed. As part of this closure, bridges, culverts, underpasses, the construction of a new railway undercarriage and superstructure, work on temporary and permanent security equipment, work on a new traction line and a new noise barrier will be reconstructed. The odd rail group will be reconstructed by 6.10.2022.
- In March, work will take place on the railway superstructure in the section Radotín km 9.3 (approx. Bus stop Vrážská) – Velká Chuchle km 7.3 (approx. Bus stop Zahradnictví), work is also underway on platform No. 1 in Velká Chuchle, related cabling work zab.zař. and low voltage and high current, lighting, etc., as well as work on the shelter, work on the door frame wall and underpass. Work is also underway on the railway undercarriage and subsequently the superstructure in the section from km 6.3 – Barrandov branch. There will be finishing and finishing work on the bridge in Podjezd Street, followed by work on the roadway and cable network relocations.
- Work on the underpass in Radotín: Underpass at the crossing The part of the concrete is already finished, there will be finishing work and fencing work, then the internal work will begin – laying paving, tiling
- Construction work on a new technological building in Malá Chuchle, work on a dispatch building in Radotín and work on a traction currency in Malá Chuchle.
- Work begins on the equipment of technologies in the technological building and in the dispatch building and in the traction change
- Work is underway on the cable duct at the dispatch building and along this side, work on the basis of shelters
- Work will begin on flood protection measures, the related relocation of cable networks, road demolition and the subsequent establishment of flood protection measures.
Overview of known restrictions for the month of March 2022 + outlook
Road restrictions / closures:
– 1/5 / 20-31 / 12/22 an entrance and exit to the construction site equipment will be set up in Mezichuchelský opposite Hornbach
– 1/6 / 20-30 / 11/22 there will be an entry and exit on the construction site in Mezichuchelská u „esíčka
– 31/7 / 20-30 / 4/22 closure of the underpass at the Rozmarýn restaurant
– 13/3 / 21-12 / 22 tunnel closure in Prvomajová street, 8/9 / 21-15 / 7/22 possible pedestrian crossing
– 22/9 / 21-11 / 4/22 underpass closure under the track in Podjezd street
– 22/9 / 21-11 / 4/22 commissioning of a temporary crossing in Paroplavební x Zbraslavská Street
– 13/9/21 – 10/6/22 – restriction of the connection lane on Strakonická behind the Barrandov Bridge towards Strakonice
– 11/10/21 – 24/5/22 – forays and exits from the building in Radotínská / Vrážská street, local restrictions Give way to the oncoming vehicle
– 22.10.21 – 15.3.22 – no standing at Rymáni and Ke Zděři
– 5.2.22 – 6.10.22 – crossing of the crossing in Velká Chuchle
– 2/5/22 – 5/6/22 – restriction of one lane in Radotínská street from the crossing in Velká Chuchle approx. 200 m towards Radotín
– 7/3/22 – 15/7/22 – restriction of one lane and then complete closure of Vrážská street (near Prvomajová – near Janka) from 2.5.22 due to the implementation of an anti-flood measure
– 9/5/22 – 17/6/22 – sewer connection on Vrážská Street, near the dispatch building, restriction of one lane and possibly a sidewalk
– 10/6/22 – 30/6/22 – closure of the Zbraslavská cycle path
– 30.11.22 – crossing closure Na betonce
Rail restrictions / exclusions for the month of March 2022:
– non-stop – for the Velká Chuchle stop: 8/9 / 21–10 / 6/22 two tracks closer to the river will be excluded
– non-stop – for the Radotín stop: 8/9 / 21–10 / 6/22 tracks closer to the river will be excluded (in operation only the new island platform and the temporary platform outside the track from the side of Prvomajová street, ie opposite the station building)
– night – there will be a stoppage of operation, at night from 3/4 – 4/5, then from 7/8 – 11/12
– night – at night from 28/2 to 1/3 – 2/3 and further from 5/6 – 6/7 and further 27/28 – 31/3 to 1/4 there will be traffic only through Krč
Restrictions in ŽST Praha Radotín in areas for the public:
– 8/9 / 21–10 / 6/22 for the Radotín railway station, the original platforms closer to the river will not be operated
– 1/4/21 – 12/22 – impenetrable underpass over the entire track – use a temporary footbridge to cross the track
Restrictions at the Praha Velká Chuchle stop in the public areas:
– March 22 – October 22, a new platform (by the forest) will be operated for the Velká Chuchle stop, with access coming through a new underpass
source: Railway administration
Related