SKM Warszawa has concluded the tender for P4 Impulsów 35WE
Fast Urban Railway 35 contractors of P4 services, fourth level service, EU service of vehicles with 35 works with works and planned as well as works and unplanned.
All bids were submitted to the tender:
- Usługi Transportu Publicznych Sp. z oo with the price for the range of the table PLN 45 309 510 and for the option PLN 4 547 499.8. Delivery time up to 64 days. The offer was rated at 100 points.
- PESA Mińsk Mazowiecki SA with the price for the range of the table PLN 46 217 250.00 and for the option PLN 6 783 573.00. Delivery time up to 69 days. The offer was rated at 88.78 points.
- Newag SA with the price for the range of the table PLN 54,243,000.00 and for the option PLN 6,517,511.70. Delivery time up to 64 days. The offer was rated at 84.76 points.
- Railway Vehicle Service sp. Z oo sp.k. with the price for the table PLN 54,243,000.00 and for the option PLN 5,189,455.00. Delivery time up to 69 days. The offer was rated at 82.43 points.
The offers check the services according to the following criteria: price per value range – 65% and service completion date – 20%. The offer submitted by the Public Transport Service was indicated as the most advantageous.
To finance the order, SKM Warszawa wants to transfer PLN 20 77 987 338, including PLN 68 007 438.00 gross for the basic order and PLN 9 979 900.20 gross for an option. Complete additional unplanned work. The selected offer is therefore much cheaper than the contracting authority now.