It has been revealed when the Sas utca underground car park will be completed
The underground garage provides 207 parking spaces on four levels in an area of seven thousand square meters. Service rooms, social blocks and a smart city management center will also be located in the building. It is also possible to accommodate bicycles and motorbikes, the building will be completely barrier-free, and there will also be 27 electric charging stations in the underground garage, so we are also considering battery vehicles when building a garage
explained László Papp. He pointed out that there was another part of this project: one above the underground garage incubation house would build, however, this development was reclassified among the programs of the 2021-2027 EU cycle. According to the plans, the office building is a to the Old Town Hall is being built, so a rectangular building complex will form here in the future.
No sinking
The mayor thanked the residents for their patience and then pointed out that such a large-scale investment in a historic city – the gross cost of which is HUF 4.7 billion – can be realized at the cost of serious sacrifices. From the point of view of traffic in the city center, he considers it extremely important that the number of parking spaces has increased, as this will make the city center even more livable. Tamás Hegymegi, the technical director of HUNÉP Zrt., said at the event that it is a particularly big challenge for the company to be able to work on such a large project, and also a great honor.
There has never been such a large gap wall construction project in Debrecen. What is special is that the area is surrounded by buildings, and it is particularly important that such large-scale land extraction does not damage the surrounding buildings, so we will install a monitoring system on the roof of the house opposite the construction site.
he declared. Tamás Hegymegi emphasized that the optical head monitors the movement of the surrounding buildings and registers the amount of subsidence in the given building until the end of the construction. So far, these subsidences are well within the limit, and the buildings have not yet been damaged.