The representative of the DK parliament makes a false statement about the battery factory in Debrecen – Debrecen news, Debrecen news | Debrecen and Hajdú-Bihar county news
The parliamentary representative of the DK makes a false statement about the battery factory in Debrecen
Author: Tamás Rituper | [email protected]
Published: 08.12.2022. 10:47 | Update: 08.12.2022. 11:00 a.m
Debrecen – Zoltán Varga claims that they are working without a permit in the area of the CATL battery factory, but this is not true.
He published photos of machines on his Facebook page Zoltán Varga, parliamentary representative of the Democratic Coalition in Debrecen, which he made in the Southern Economic Zone, in the area where CATL is building the battery factory. In the representative’s post, the representative claims, “all of these are really all that the factory certainly does not have the construction permit, as the documentation required for the authorization procedures of the specialized authorities was also submitted by the management of the Chinese CATL factory just two weeks ago!”
According to the representative, it proves that the government, the municipality and CATL do not comply with the laws, and according to his promise, he will demand this from the competent Hajdú-Bihar County Government Office “in the case of construction without a permit”, together with the construction of the factory. or the immediate cessation of work related to its preparation.
However, Zoltán Varga is wrong, the works were not authorized.
As the Dehir.hu wrote it on November 23the Hajdú-Bihar County Government Office issued a construction permit to Contemporary Amperex Technology Co. Limited (CATL) for the landscaping of the area of the planned building factory and the deep foundation works of four buildings in the Southern Economic Zone of Debrecen.
This is the very first step in the authorization procedure for the construction of the battery plant, and it is intended exclusively for the preparation of the area, the removal of humus and the deep foundation work of four plant buildings.
It was previously announced that according to the schedule, the next step will be for the company to submit the documentation required for the environmental protection licensing procedure, after which the environmental protection licensing procedure can begin, during which a public hearing will also be held. The building permit application for the buildings and technology can only be submitted by CATL after this.
Zoltán Varga, the cases he is talking about are the environmental protection permit procedure, and his application in this regard was indeed regularly provided by CATL, this is completely public (available here), and as promised,
in January a public hearing is also held in Debrecen.