Warsaw. Tram to Wilanów. Preparations for the new organization of traffic organization for the time of construction are underway. List of handicaps
In the queue, they are preparing to build a railway line to Wilanów. The main works will not start until the end of August, but you will start to take into account the difficulties now. The Town Hall is a functioning organization that is scheduled for the duration of the works.
As we informed on Wednesday on tvnwarszawa.pl, the town hall announced that works on the construction of the tram line for Wilanów will start at the end of August. However, officials did not provide any questions regarding the end or where elsewhere officials addressed the handicap. Only Thursday has already appeared, another message to organize the traffic. Please let us know that on Friday, August, railwaymen will start working on the streets of the new street
Residents may expect changes to the Puławska, Spacerowa, Belwederska and Jana III Sobieski streets under construction. At the beginning, work was on the first steps, the first steps, on the Krokiławska street to the junction of Jan III Sobieski by Beethoven. “Limitation of car and car, and a complaint spot at the intersection with Goworka and Waryńskiego streets. Traffic will take place here, on Goworka, Spacerowa, Belwederska and Jan III Sobieski streets, along the road in motion. they will go on separate bus lanes on Puławska, Belwederska and Dolna streets – behind the town hall.
The office opened the entrance to the website tramwajdowilanowa.pl. Residents can drive traffic through your site to a newsletter with news about investments and changes in the organization. The plans also provide an e-mail address for asking questions about the topic and issues related to the topic.
Preparations for the construction of a tram to Wilanów
On August 12, the trams will begin the preparation of elements that can be tested by periodically organizing the essential construction works on the market. In lane III, the barriers will balance the roadways of Jana Sobieskiego and Belderska streets in an equal, temporary balance, as well as exits to positions and stops. Drivers must make sure that during the work or even there will be left lanes for footbridges for the implementation at Kostrzewskiego and van Beethoven, Hańcza, Chełmska and Sułkowicka Streets. Pedestrians temporarily get with a higher overrun to cross Jana III Sobieskiego Street on the south side with Dolna and Chełmska.
On Puławska street, tram drivers will build a lacing through the return lane. at the height of Willowa and Grażyna streets. During these works, the left lanes of both Puławska lanes will be left with no traffic at the same time.
At the intersection of Puławska and Goworka it is necessary to widen the road. The City Hall does not state that the works will be performed along the lane in the area of roadways and islands. During them, turning left from Waryński Street into Goworka Street, she will be able to use only one lane. Also – also on one lane – there will be a left turn from Goworek to Puławska.
The island separating the road at the intersection of Belwederska, Gagarina and Spacerowa will be removed. “For people who have the right island matching, they also have seat belts.
25 instead of 45 minutes
The new route will start at Puławska Street at Goworka Street. As much as 22 meters, another level towards the Lower tram and Spacerowa. Write the line will run straight along Belwederska and Sobieskiego streets towards Miasteczko Wilanów. Travel by tram with access to this station to the station station approximately 25 minutes. The City Hall points out that it is much shorter than covering the same route – peaks were recorded, which were now used for 45 minutes.
Budimex is responsible for the implementation of the investment. All works are to be completed in the first quarter of 2024. The total value of construction works is over PLN 685 million.