Warsaw. Marszałkowska. Reconstruction of the website at Bankowy Square. Road workers announced the completion of the signaling
Road workers say that even before Christmas there is signaling at the engine crossing for the Marshal’s function, in the area of Bankowy Square. Work on the reconstruction of zebra superheroes will continue until the end of this year.
The passage through Marszałkowska Street to the height of Senatorska and Elektoralna Streets fell as one of the safe ones in the capital. On the nearly three-meter-long Central European construction site to the Bank’s construction site, there is only a meeting place, although pedestrians here can always overcome it in queues and six lanes from the peninsula after the constitution. Four years ago, it was changed into a so-called working crossing, with flashing LEDs in the asphalt to alert drivers to a pedestrian crossing. However, so that it does not solve the problem. During the pass-through security audit, it scored very low. The auditors recommended the production of the signaling.
Works started in November. Road workers informed on Tuesday that the investment is already at its halfway point. At the crossing it has been written with traffic lights, the contractor is working on the masts. The new signaling will display the vehicles in the new version of the track and
WHY DO 7 PEOPLE KILL EVERY DAY ON POLISH ROADS? WATCH GO ON TVN24 >>>
Change at the inlet, intersection with Elektoralna
As part of the reconstruction, the geometry of the intersection of Marszałkowska and Elektoralna is also corrected. “Its inlet is on a new profile, thanks to which it is located on the widening on the south-west corner.
Design also by place. Pre-assembled slabs with protrusions, where it will be ready when entering, ready curbs are also ready. There will be a designated bicycle path next to it, which will eventually be connected to the new bicycle path in the marshal’s reconstruction as part of the activities from Bankowy Square to Królewska Square. “Marshals’ traffic services in the direction of shaping the south will also adopt plans to replace the street layout workers on this” – they tie the signpost.
Future works are to last until the end of the year, but road engineers are optimistic that the signaling may be ready before their final acceptance. “It is possible that if the contractor maintains the current pace of works, the signaling will be launched before the Christmas and New Year period” – we read in the communication.
The contractor is the capital company Podkowa, which valued its offer at PLN 837,000. The agreement of the day is at the beginning of November and assumes 45 realizations for investments from investments.