Zizkov is solving a threatening traffic situation. The municipality promises to complete the work soon Transport News Pražská Drbna
Prague’s Žižkov has been facing a very difficult traffic situation for several days now. Drivers spend more time in convoys on Jana Želivského, Olšanská, Táboritská or Koněvova streets than they would like. The management of Prague 3 let the public know that the city, not the city district, is responsible for the unfortunate coordination of repairs. Following a joint meeting, the municipality undertook to complete the existing work as soon as possible.
Joint meeting of Ptáček, Hřib and Scheinherr
The reason for the columns that are being built in Jana Želivského, Olšanská, Táboritská or Koněvova streets, hence Husitská, is the large number of closures. “We have been dealing with the situation with the municipal authorities for several days now,” said the mayor of Prague 3 yesterday Jiří Ptáček (TOP 09).
On Thursday morning, Mayor Zdeněk Hřib (Pirates) convened a joint meeting with the participation of Adam Scheinherr Transport Square (Prague itself) and representatives of other organizational units of the capital, which are involved in the closures in Prague 3. “Prague 3 to start dissatisfaction with the need to coordinate and to ensure that no emphasis is placed on duration in the selection of contractors, ” Mayor Ptáček explains his position.
Tuesday, 16 November 2021, 18:00
Drivers in Prague’s Žižkov have been bothered by larger traffic jams since yesterday. Yesterday, another place in the same …
Repairs will be completed as soon as possible
The management of the capital is aware that the role of repair coordinator belongs to the municipality, and so it has committed itself to completing the repairs as soon as possible. In addition, measures for the tram department in Seifertova Street will be introduced from Monday.
The following stages of the reconstruction of Koněvova Street will compete with a 40% weight for construction time.
1) Repair of the sewerage system on Želivského in the section from the intersection with Olšanská Street towards Vinohradská Street
Investor: Pražská vodohospodářská společnost as
Planned termination of the event: December 20, 2021
2) Trocnovská Street – replacement of the road surface with a new asphalt road
Investor: Technical Administration of Roads m Prague, as
Planned termination of the event: December 5, 2021
3) Reconstruction of the water supply system in the Rokycany – Černínova section
Investor: Pražská vodohospodářská společnost as
The actual end of the event. agreed on 15 January 2021, further timing of the implementation of subsequent stages will be part of the coordination
4) Reconstruction of Koněvova Street in the Rokycany – Černínova section
Investor: Technical Administration of Roads m Prague, as
It is already open for one-way traffic and thus the planned end of the event in both directions is two days before the deadline of November 30, 2021, November 28, 2021.
5) Replacement of the backbone water supply feeder from Káraný to Vinohradská waterworks on Vinohradská street.
Investor: Pražská vodohospodářská společnost as
Planned termination of the event: 30. 04. 2022, release of traffic from 21. 12. 2021 to 3. 1. 2021
6) Excavation of sewers at the intersection of Jana Želivského – Olšanská streets
Investor: CENTRAL GROUP 32, investiční sro
Planned termination of the event: December 21, 2021
7) Relocation of the traction line to Jan Želivský at the intersection with Jeseniova Street
Investor: CENTRAL GROUP 32, investiční sro
Planned termination of the event: December 13, 2021