Zan repair of the track on Bubensk nbe, trams will not run until November
The Transport Company of the Capital City of Prague (DPP) instead of the tram in the section from Vltavsk to Dlnická will introduce an X25 bus service between Strossmayer Bridge and Maniny.
Trams are repaired to cut the well at night from the bird on November 5 to Saturday, November 6, with the encounter of non-traffic, ie around midnight.
On all tratches in Prague, we are gradually replacing the old BKV panels with a new technology of placing the tram body on a concrete slab and fixing the rails with the W-tram system. Thanks to this, the tram operation on such reconstructed tratches is a hit, said Jan Urovsk, technical director of DPP.
Traffic restrictions Bubensk nbeTram route changes
Changes in tram stops and spare bus transport X25
X25 line stops: Maniny nstupn, Tusarova, Prask trnice: in trams tram
Changes in bus stops until January 23, 2021 until about 0:30 p.m. For lines. 156, 905 and 911, the Vltava region, Strossmayerovo nmst, resp. For a long time, Captain Jaroe piblin on us 100 meters back to the end of the X25 line under the Negrelli viaduct. Source: DPP |
Reconstruction on Bubensk is the first of nine stages, which will be carried out gradually so that their impact on public transport and individual transport is as small as possible.
In the first stage, we will reconstruct approximately 230 meters of track in coordination with TSK. Five years later, the reconstruction of the following sections around Prask trnice, which we will carry out in connection with the start of the construction of the Holeovice Karln lion, added Urovsk.
The DPP event took place in parallel with the repair of the road in Pilehl Argentinsk Street, which started on Wednesday 13 June and lasted until 22 June. In the Argentinsk ᠖ Plynrn TSK section, the light signal device is repaired.
The second stage of reconstruction in Argentinsk is completed from June 23 to June 31 and aunt from November 1.
The system of works in Argentinsk Street is as high as possible, which is a preparation for the reconstruction of sewers, gas pipelines, roads and the promenade Bubensk nbe, Argentinsk Street and the lion leading from Holeovice to Karlna (HolKa).
Traffic restrictions Argentinsk
Source: TSK Prague |