We will replace the surface on Ludna Street. Drivers of traveling flowers
In the fall of last year, we performed a “facelift” at ul. Ludna. First of all, we moved parking from the sidewalks to the road, on which we created parking lanes. We renovated the release from the pavement cars, improved the side made for assembly and made the slab strips. In addition, we planted a low grade green. Now we will complete the changes by renovating the surface.
Difficulties and detours
Work with this mechanism will start on Friday, October 1 at approx. 22 and will last until Monday, October 4, at 4 a.m. At that time, the entrance to ul. Ludna will be closed – from the intersection with Kruczkowskiego, Książęca and Rozbrat streets. Drivers will not be able to turn into ul. Ludna with ul. Kruczkowskiego and ul. Rozbrat, nor drive straight into ul. Ludna with ul. Książęca. These bans do not apply to floating vehicles, ambulances and drivers wishing to reach ul. Orłowicz.
On the road of ul. Wioślarska towards Wilanów, in the area there is an intersection with ul. Ludna, from the resistance movement, the right lane. Drivers also could not be the owners of the gateway between the Wisłostrada road in the direction of ul. Ludna. Access to the city. Orłowskiego will be provided by Wilanowska and Czerniakowska streets.
Drivers moving along ul. Rowing to the north, they may have been able to bypass the inconvenience. They will do so by turning back at the junctions of the Poniatowski bridge and going along the Wisłostrada (Wioślarska and Solec streets) to Górnośląska and Rozbrat streets. Otherwise, it inhibits the return to the new currency and the Indian Avenue again
The detour of the section where the pavement will be replaced will also lead along ul. Nowy Świat and Al. Jerozolimskie to Wisłostrada. ul. Good management led by the streets of Czerwonego Krzyża and Kruczkowskiego. From Kruczkowskiego and Książęca Streets, through Rozbrat and Łazienkowska Streets, the detour will lead to Wisłostrada. Current detour from ul. Solec will also run along Łazienkowska and Rozbrat streets, and from ul. Dobra – along Tamka and Kruczkowskiego streets.
During weekend works at ul. People’s pedestrians led to the nearby crossings for the proceedings, in draining the council’s progress.
Public transport
In connection with the construction of the pavement route, three bus lines will be changed during the works: 118, 127 and 166. For line buses 118 and 127 – to the north – from ul. Książęca, there will be a route running along Kruczkowskiego and Tamka Streets. In the whole direction, from ul. Dobra, they will go along Zajęcza, Topiel and Kruczkowskiego streets.
Bus line 166 from pl. Trzech Krzyży will go straight to Al. Jerozolimskie, the last ones will reach the Poniatowski and reference bridge.
The operation of the stops: “Czerniakowska 01”, “Solec 01”, “Solec 02”, “Al. 3 Maja 01 “,” al. 3 Maja 02 “,” Jaracza 01 “and” Jaracza 02 “will be suspended.
Detailed information on changes in traffic organization, repairs and investments can be found at: www.infoulice.um.warszawa.pl and www.facebook.com/infoulice, while messages on the routes of Warsaw Public Transport vehicles can be found at: www.wtp.waw.pl. Additionally on the site City Contact Center, Warsaw 19115 You can report SMS reporting about traffic obstruction in the capital.